Pumwani Lucky Summer Dispensary
One of three health facilities (combined cost KSh 869 million) that the Auditor-General found abandoned by the contractor; inspection in September 2023 found works had barely started.
- Location
- As named in the audit (location to be confirmed)
- Responsible department
- Health
- Started under
- Not established
- Original budget
- Not available
- Contract value
- Not available
- Amount paid
- Not available
- Contractor
- Not established
- Reported completion
- Not reported
- Current verified status
- Abandoned
- Estimated cost to complete
- Not available
Reason for delay
Contractor abandoned the project (Auditor-General).